Dung Quat Refinery’s Expansion

The Dung Quat Refinery’s Expansion Project is an initiative to increase the refinery's capacity up to 8.5 million tons per year, improve energy efficiency, and meet stricter environmental standards.

Capacity: 6.5 - 8.5 million tons/year


Location: Dung Quat Economic Zone, Binh Son district, Quang Ngai province


Owner: Binh Son Refining and Petrochemical JSC


Investment cost:

  • Total: $1.49 billion

  • Financing source: $503 million from equity, $987 million from loan


FEED (Front-End Engineering Design):

  • Contractor: Amec Foster Wheeler (Wood Group)

  • Value: $25.6 million

  • Duration: 7 months


Planned EPC construction time: 37 months


Expected COD: 2028